New plant approved for Gazprom Neft’s Russian refinery

logo_gazprom-bigRussian gas producer JSC Gazprom Neft is proceeding with the second phase of construction of the biological wastewater treatment system at its 12.15 million tonne/year Moscow refinery.
The project documentation for the installation was approved in December 2014 by the Russian federal agency Glavgosekspertiza, responsible for standards and quality control.

The two second-phase biological treatment plants will have a total capacity of 1,400 cu m/hr and will be divided into two zones covering an area of 6,400 sq m and 18,000 sq m respectively, the company said.
The biological treatment installation will consist of a chain of processes including membrane bioreactor units, two-stage flotation, a carbon filter, dewatering of activated and oily sludge, and reverse osmosis.

Activated sludge, containing various microorganisms that act together to absorb organic matter, nitrogen and other petroleum products and pollutants, will be used in combination with mechanical filtration through a bioreactor to remove almost all industrial effluents from the refinery’s wastewater, Gazprom Neft said.
Once completed in 2017, the multi-stage treatment system will significantly reduce the refinery’s water consumption, allowing 75% of the water to be returned to the plant’s production cycle.

The new system will improve the quality of the water discharged by the refinery to match that found in fisheries, reducing the need for wastewater treatment by local authorities by a third.

These treatment plants will form part of a single installation with an underground mechanical treatment plant completed at the refinery in 2012 as part of the first phase of the project, Gazprom said in April 2014.

The implementation of the treatment system, like the other emission-reduction projects, is part of the Moscow refinery’s 2013-2020 renovation and modernisation programme, says Arkadly Egizaryan, CEO of Gazprom Neft’s Moscow refinery.

Once completed, the modernisation programme will increase the Moscow refinery’s overall design capacity to 18.15 million tonnes/year.