Kazakhstan: refinery modernisation programme moves forward

The State company KazMunaiGas (KMG) of Kazakhstan has secured financing from the Development Bank of Kazakhstan JSC (DBK) for the ongoing modernisation of the refining and petrochemical complex Pavlodar with a capacity of 6 million tonnes per year.

DBK will cover about 25% of the total cost of more than 1.2 billion dollars required for the modernisation project, in the form of a 10-year loan. The remaining 75% has been financed mainly through club-deal loans from Japanese banks, DBK said.

In addition to improving the quality of petrol and diesel production to comply with the technical specifications set by the Eurasian Economic Commission (EEC) for emission classes K4 and K5, equivalent to the European Euro 4 and Euro 5 environmental standards, the Pavlodar modernisation project will also increase the plant's crude processing capacity to 7 million tonnes per year.

While the Pavlodar refinery was originally designed to process a West Siberian crude blend, the overall upgrade, once completed, will enable the complex to process up to 5 million tonnes per year of crude oil from Kazakhstan as well, DBK said.

The start-up of the first phase of the modernisation project, consisting of two units, is scheduled for January 2016, when the refinery will be able to produce K4-standard fuels.

Also according to the bank, the remaining work on the refinery overhaul is expected to be completed in 2017. In particular, the Pavlodar upgrade programme involves revamping ten of the plant's units, including crude distillation, vacuum distillation, kero hydrotreating, diesel hydrotreating, Merox unit, naphtha hydrotreating, vacuum gas oil unit, FCC unit and catalytic reforming unit, as well as utilities and storage.

Atyrau upgrade: state of the art. 

According to DBK, which financed 45% of the project, the first phase of a 2.9 billion dollar revamp of KMG's 104,000 barrel-per-day Atyrau refinery is nearing completion. However, no completion date for the first step of the project has been announced. A second phase of reconstruction and modernisation at Atyrau, involving the construction of a deep oil conversion complex at the site, has been awaiting full financial backing since May 2014.

KMG said it aimed to complete the modernisation projects launched in 2012 at the three refineries in Kazakhstan by 1 January 2016, as part of the 2010-14 Programme for the development of the Oil & Gas sector of the Republic of Kazakhstan, which aims to strengthen the country's overall crude distillation capacity to reach production of 18.5 million tonnes per year, as well as to improve the quality of production yields.